Doug Kerr
Well-known member
This is one of a series of presentations of photographs of an ongoing upgrade to a 345 kV electrical transmission line that passes near my home. The upgrade consists of the addition of a second circuit to increase the overall capacity of the line.
Douglas A. Kerr, Aerial Transmission I
Here we see a 120' tall transmission tower being moved to an extended base in order to raise its overall height by about 25'. As I understand it, this is required to meet current standards for conductor clearance over urban structures. (The line was originally built in 1979.)
These tower relocations were made after the addition of the new second circuit (on the far side of the tower in this view). Otherwise, the unbalance in weight of the original circuit conductors would have made it impossible to move the tower with a single crane.
In fact, to minimize imbalance caused by small weight and tension differences in the two sides, the outermost conductor pair on each side was removed from the tower and temporarily supported by a crane (seen on the right, with the other one seen behind the tower).
The "original circuit" conductors remaining on the tower had to be removed from their suspensions and temporarily put into pulley-like stringing blocks ("dollies") so that the tower could shift while the conductors retained their location. On the new side, the conductors were still in the dollies through which they had been placed just last week.
The foreman said that his crew can usually do three of these relocations in a day.
Douglas A. Kerr, Aerial Transmission I
Canon EOS 40D, Sigma 18-200 mm f/3.5-6.3 DC at 18 mm, ISO 400, F/14, 1/512 sec.
100% x 89% crop, presented here at 31% of original camera resolution.
100% x 89% crop, presented here at 31% of original camera resolution.
Here we see a 120' tall transmission tower being moved to an extended base in order to raise its overall height by about 25'. As I understand it, this is required to meet current standards for conductor clearance over urban structures. (The line was originally built in 1979.)
These tower relocations were made after the addition of the new second circuit (on the far side of the tower in this view). Otherwise, the unbalance in weight of the original circuit conductors would have made it impossible to move the tower with a single crane.
In fact, to minimize imbalance caused by small weight and tension differences in the two sides, the outermost conductor pair on each side was removed from the tower and temporarily supported by a crane (seen on the right, with the other one seen behind the tower).
The "original circuit" conductors remaining on the tower had to be removed from their suspensions and temporarily put into pulley-like stringing blocks ("dollies") so that the tower could shift while the conductors retained their location. On the new side, the conductors were still in the dollies through which they had been placed just last week.
The foreman said that his crew can usually do three of these relocations in a day.